Annual Accounts 2016

2016 Statutory Accounts for BHOEC have now been published.

Continue reading

Posted in Notices | Leave a comment

Annual Accounts 2015

2015 Statutory Accounts for BHOEC have now been published.

Continue reading

Posted in Annual Accounts | Leave a comment

AGM Minutes 9th February 2016

Minutes of the 35th AGM of the Birds Hill Oxshott Estate Company

Held on the 9th February 2016 at St Andrew’s Church Hall,

Oakshade Road, Oxshott at 8pm.
Continue reading

Posted in Minutes of Meetings | Comments Off on AGM Minutes 9th February 2016

Speed Table Works

Dear Southside Residents,

Please be advised that a program of repair works (funded by the contractor) is being  carried out to a number of speed humps within the Southside of the Estate commencing on Monday 7th December.

During these works the Southside gates onto Fairoak Lane will be opened to keep traffic flowing.

Details of the planned works can be found on this PDF: Speed Table Works Map Plan

Regards

Gavin
GAVIN DERRIMAN
ESTATE MANAGEMENT

Posted in Notices | Comments Off on Speed Table Works

South Side Road Programme, Phase II – W/C 12th October

Birds Hill Road

  • Monday – Tue – Topsoil, Seed and verge works
  • Tuesday – Removal of rocks and boulders

Leys Road

  • Mon – Tue – Carrying out any driveway or kerb repairs required
  • Tue – Wed – Topsoil, Seed and verge works

Broomfield Ride

  • Tue – Thur – Topsoil, Seed and verge works
  • Thur – Fri – Laying new surface course at top end of road
  • Thur – Fri – Carrying out patch repairs to Birds Hill Rise

Spicers Field

  • Thur – Fri – Laying new asphalt surface course

Stokesheath Road North

  • Thursday afternoon plane off 15mtr patch
  • Friday midday resurface patch

At the end of the week there will be MTS carrying out drainage clearance works and CCTV surveys of the existing required pipes on all four road Leys, Birds Hill, Broomfield and Spicers

Posted in Notices, South Side Road Works Phase 2 | Comments Off on South Side Road Programme, Phase II – W/C 12th October

South Side Road Programme, Phase II – W/C 5th October

Birds Hill Road

Monday – Friday:

  • Mon – Tue – Raising Ironworks in the road
  • Mon – Tue – Carrying out landscaping of the verges
  • Wed – Laying asphalt surface course

Leys Road

Monday – Friday:

  • Mon – Tue – Laying Asphalt base and binder courses along length of road
  • Wed – Carrying out ironworks in road
  • Wed – Landscaping verges
  • Thur – Laying new asphalt surface course in road

Broomfield Ride

  • Mon – Tue – Landscaping verges
  • Thur – Fri – Laying new surface course in road

Spicers Field

  • Mon – Tue – Raising ironworks in road
  • Thur – Fri – Laying new asphalt surface course
Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 21st September

Birds Hill Road

Monday – Friday:

  • Monday – Tue – Driveway Repairs and Granite Sett installation
  • Mon – Thu – Carrying out ironwork adjustment

Leys Road

Monday – Friday:

  • Wed – Fri – Excavation of existing road
  • Wed – Fri – Installation of new Tensar Geogrid and sub base
  • Tue – Wed – Driveway Repairs and Granite Sett installation

Broomfield Ride

  • Tue – Thu – Repairs to granite setts and kerbs and Driveway repairs
Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 14th September

Birds Hill Road

Monday – Friday:

  • Monday – Lay base course along entire road
  • Tuesday – Lay binder course along entire length of road
  • Wed – Fri – Carry out driveway and verge reinstatement works

Leys Road

Monday – Friday:

  • Mon – Fri – Carry out kerb crossings on two number driveways
  • Carry out any excavation preparation of road surface

Broomfield Ride

Tuesday – Friday:

  • Carry out any kerb repair works
Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 24th August

Birds Hill Road

Monday – Friday:

  • Monday – Removal of the gates
  • Mon – Thu – Plane off existing surface of the road and grade & compact to levels.
    • DELAYED TO NEXT WEEK DUE TO ADVERSE WEATHER CONDITIONS
  • Wed – Fri – Carry out full depth reconditions in 2no sections of Birds Hill road.
  • Install ramping to driveways and access.

Leys Road

Monday – Friday:

  • Mon – Fri – Raise, repair and relay certain driveway entry blocks to suit new road levels
  • Wed – Fri – Complete drainage works
  • Wed – Fri – Clean road and prepare ready, for planing works the following week.

Gate Removal Broomfield Ride and Birds Hill Road

Tuesday – Thursday:

  • Week commencing 24<supthAugust, the entrance gates at Broomfield Ride and Birds Hill Road will be removed whilst the roads are reconstructed. During this time the gates will be sent away for preparation repair and powder coating.
Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 17th August

Broomfield Ride

Monday – Wednesday:

  • Mon – Wed – Installation of new table top speed ramp by Leys Road Junction road closure until complete.

Leys Road

Monday – Friday:

  • Mon – Wed – Installation of final Gullies
  • Wed – Thu – Completion of drainage works in ditches

Birds Hill Road

Tuesday – Thursday:

  • Making good behind driveway installations
Posted in Notices, South Side Road Works Phase 2 | Leave a comment