South Side Road Programme, Phase II – W/C 24th August

Birds Hill Road

Monday – Friday:

  • Monday – Removal of the gates
  • Mon – Thu – Plane off existing surface of the road and grade & compact to levels.
    • DELAYED TO NEXT WEEK DUE TO ADVERSE WEATHER CONDITIONS
  • Wed – Fri – Carry out full depth reconditions in 2no sections of Birds Hill road.
  • Install ramping to driveways and access.

Leys Road

Monday – Friday:

  • Mon – Fri – Raise, repair and relay certain driveway entry blocks to suit new road levels
  • Wed – Fri – Complete drainage works
  • Wed – Fri – Clean road and prepare ready, for planing works the following week.

Gate Removal Broomfield Ride and Birds Hill Road

Tuesday – Thursday:

  • Week commencing 24<supthAugust, the entrance gates at Broomfield Ride and Birds Hill Road will be removed whilst the roads are reconstructed. During this time the gates will be sent away for preparation repair and powder coating.
Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 17th August

Broomfield Ride

Monday – Wednesday:

  • Mon – Wed – Installation of new table top speed ramp by Leys Road Junction road closure until complete.

Leys Road

Monday – Friday:

  • Mon – Wed – Installation of final Gullies
  • Wed – Thu – Completion of drainage works in ditches

Birds Hill Road

Tuesday – Thursday:

  • Making good behind driveway installations
Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 3rd August

Broomfield Ride

Monday – Friday:

  • Mon – Fri = Installation of new table top speed ramps, these will be carried out 1 at a time as the section of road will be closed for 2-3 days at a time.

Leys Road

Monday – Friday:

  • Mon – Wed – Excavation and re-grading of ditches
  • Wed – Thu – Completion of drainage works

Birds Hill Road

Tuesday – Thursday:

  • Making good behind driveway installations
Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 20th July

Birds Hill Road

Monday – Friday:

  • Mon – Tue – Topsoil and make good verges

Leys Road

Wednesday – Friday:

  • Tue – Fri – Excavation of new kerbline on Northern Verge
  • Mon – Wed – Installation of new kerbs on Southern Verge
  • Wed – Fri – Installation of kerbs on Northern Verge
  • Wed – Fri – Installation of new road gullies
Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 6th July

Birds Hill Road

Monday – Friday:

  • Mon – Thu – Installation of new kerbs along entire southern verge
  • Wed – Thu – Installation of new Granite setts across driveways
  • Tue – Fri – Installing new gully pots and connections
Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 29th June

Birds Hill Road

Monday – Friday:

  • Mon – Fri Excavation of kerb line along the Southern verge
  • Wed – Thu Small areas of road widening on the Southern verge
  • Mon – Fri Installing new kerb line on Northern verge

Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 22nd June

Birds Hill Road

Monday – Friday:

  • Mon – Wed  Excavation of kerb line along the northern verge
  • Mon – Tue  Small areas of road widening on the northern verge
  • Tue – Thu  Installing new kerb line on Northern verge
  • Wed – Fri  Excavation of kerb line along southern verge
  • Thu – Fri  Installing new kerbs along southern verge
Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 8th June

Spicers Field

Monday – Friday:

  • Mon – Wed – Excavation/clearing of drainage ditches and cleaning pipes
  • Grading verges and placing layer of topsoil
  • Making good all driveways and verges

Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 1st June

Spicers Field

Monday – Wednesday: Resurfacing Works

  • Monday – Lay Base course from Princes Drive
  • Tuesday – Complete base course and start Binder course from Princes Drive
  • Wednesday – complete Binder course
  • Thursday/Friday – carry out ditch excavation works

Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 25th May

Spicers Field

Tuesday – Thursday: FDR Road Excavation works

  • Plane out existing road surface 300mm deep in specified sections
  • Install new Tensar geo-grid ground stabiliser
  • Lay new sub base grade and compact

NB – these three areas are, the first 80mtrs at each end of Spicers Field and the junction with Furze Field, each area will be closed for 2 days. Local residents will be notified by letter.
Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment