South Side Road Programme, Phase II – W/C 29th June

Birds Hill Road

Monday – Friday:

  • Mon – Fri Excavation of kerb line along the Southern verge
  • Wed – Thu Small areas of road widening on the Southern verge
  • Mon – Fri Installing new kerb line on Northern verge

Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 22nd June

Birds Hill Road

Monday – Friday:

  • Mon – Wed  Excavation of kerb line along the northern verge
  • Mon – Tue  Small areas of road widening on the northern verge
  • Tue – Thu  Installing new kerb line on Northern verge
  • Wed – Fri  Excavation of kerb line along southern verge
  • Thu – Fri  Installing new kerbs along southern verge
Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 8th June

Spicers Field

Monday – Friday:

  • Mon – Wed – Excavation/clearing of drainage ditches and cleaning pipes
  • Grading verges and placing layer of topsoil
  • Making good all driveways and verges

Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 1st June

Spicers Field

Monday – Wednesday: Resurfacing Works

  • Monday – Lay Base course from Princes Drive
  • Tuesday – Complete base course and start Binder course from Princes Drive
  • Wednesday – complete Binder course
  • Thursday/Friday – carry out ditch excavation works

Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 25th May

Spicers Field

Tuesday – Thursday: FDR Road Excavation works

  • Plane out existing road surface 300mm deep in specified sections
  • Install new Tensar geo-grid ground stabiliser
  • Lay new sub base grade and compact

NB – these three areas are, the first 80mtrs at each end of Spicers Field and the junction with Furze Field, each area will be closed for 2 days. Local residents will be notified by letter.
Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 18th May

Spicers Field

Monday – Thursday: FDR Road Excavation works

  • Plane out existing road surface 300mm deep in specified sections
  • Install new Tensar geo-grid ground stabiliser
  • Lay new sub base

NB – these three areas are, the first 80mtrs at each end of Spicers Field and the junction with Furze Field, each area will be closed for 2 days. Local residents will be notified by letter.
Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 4th May

Tuesday – Wednesday:

  • Carry out excavation of kerb line on Northern verge of Broomfield Ride from Leys Rd to Spicers Field
  • Install and complete new kerb line along Northern Verge between Leys rd and Spicers Field
  • Backfill verge and make good

Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – Week 5 Planned Works

Week Commencing Monday 27th April

Monday – Wednesday:

  • Carry out excavation of kerb line on southern verge of Broomfield Ride to Fairoak lane
  • Install and complete new kerb line along southern verge of Broomfield Ride
  • Backfill verge and make good

Continue reading

Posted in Notices, South Side Road Works Phase 2 | Comments Off on South Side Road Programme, Phase II – Week 5 Planned Works

Annual Accounts

2014 Statutory Accounts for BHOEC have now been published.

Continue reading

Posted in Annual Accounts | Leave a comment

South Side Road Programme, Phase II – Week 3 Planned Works

Week Commencing 13th April 2015

We will be working on Broomfield Ride between the roundabout and Spicers Field.
Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment