Category Archives: South Side Road Works Phase 2

Updates for Phase 2 of the South Side roadworks

South Side Road Programme, Phase II – W/C 22nd June

Birds Hill Road Monday – Friday: Mon – Wed  Excavation of kerb line along the northern verge Mon – Tue  Small areas of road widening on the northern verge Tue – Thu  Installing new kerb line on Northern verge Wed … Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 8th June

Spicers Field Monday – Friday: Mon – Wed – Excavation/clearing of drainage ditches and cleaning pipes Grading verges and placing layer of topsoil Making good all driveways and verges

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 1st June

Spicers Field Monday – Wednesday: Resurfacing Works Monday – Lay Base course from Princes Drive Tuesday – Complete base course and start Binder course from Princes Drive Wednesday – complete Binder course Thursday/Friday – carry out ditch excavation works

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 25th May

Spicers Field Tuesday – Thursday: FDR Road Excavation works Plane out existing road surface 300mm deep in specified sections Install new Tensar geo-grid ground stabiliser Lay new sub base grade and compact NB – these three areas are, the first … Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 18th May

Spicers Field Monday – Thursday: FDR Road Excavation works Plane out existing road surface 300mm deep in specified sections Install new Tensar geo-grid ground stabiliser Lay new sub base NB – these three areas are, the first 80mtrs at each … Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – W/C 4th May

Tuesday – Wednesday: Carry out excavation of kerb line on Northern verge of Broomfield Ride from Leys Rd to Spicers Field Install and complete new kerb line along Northern Verge between Leys rd and Spicers Field Backfill verge and make … Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – Week 5 Planned Works

Week Commencing Monday 27th April Monday – Wednesday: Carry out excavation of kerb line on southern verge of Broomfield Ride to Fairoak lane Install and complete new kerb line along southern verge of Broomfield Ride Backfill verge and make good

Posted in Notices, South Side Road Works Phase 2 | Comments Off on South Side Road Programme, Phase II – Week 5 Planned Works

South Side Road Programme, Phase II – Week 3 Planned Works

Week Commencing 13th April 2015 We will be working on Broomfield Ride between the roundabout and Spicers Field.

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

South Side Road Programme, Phase II – Week 2 Planned Works

Planned Works for Week 2 Tuesday 31st  Carrying out survey works on Broomfield ride and Spicers field. These are non intrusive works and will not close any sections of the road or require TM Set up compound/Delivery of site office … Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment

Crown Estate Road Programme, South Side, Phase II

WEEK ONE W/C 6TH APRIL Starting from the 7th April the contractors, Lafarge Tarmac are commencing works as follows : • Site clearance of timber edgings and posts with kerbline excavations on Broomfield Ride from Birds Hill Road downwards. • … Continue reading

Posted in Notices, South Side Road Works Phase 2 | Leave a comment