South Side Road Programme, Phase II – W/C 24th August

Birds Hill Road

Monday – Friday:

  • Monday – Removal of the gates
  • Mon – Thu – Plane off existing surface of the road and grade & compact to levels.
    • DELAYED TO NEXT WEEK DUE TO ADVERSE WEATHER CONDITIONS
  • Wed – Fri – Carry out full depth reconditions in 2no sections of Birds Hill road.
  • Install ramping to driveways and access.

Leys Road

Monday – Friday:

  • Mon – Fri – Raise, repair and relay certain driveway entry blocks to suit new road levels
  • Wed – Fri – Complete drainage works
  • Wed – Fri – Clean road and prepare ready, for planing works the following week.

Gate Removal Broomfield Ride and Birds Hill Road

Tuesday – Thursday:

  • Week commencing 24<supthAugust, the entrance gates at Broomfield Ride and Birds Hill Road will be removed whilst the roads are reconstructed. During this time the gates will be sent away for preparation repair and powder coating.