South Side Road Programme, Phase II – W/C 12th October

Birds Hill Road

  • Monday – Tue – Topsoil, Seed and verge works
  • Tuesday – Removal of rocks and boulders

Leys Road

  • Mon – Tue – Carrying out any driveway or kerb repairs required
  • Tue – Wed – Topsoil, Seed and verge works

Broomfield Ride

  • Tue – Thur – Topsoil, Seed and verge works
  • Thur – Fri – Laying new surface course at top end of road
  • Thur – Fri – Carrying out patch repairs to Birds Hill Rise

Spicers Field

  • Thur – Fri – Laying new asphalt surface course

Stokesheath Road North

  • Thursday afternoon plane off 15mtr patch
  • Friday midday resurface patch

At the end of the week there will be MTS carrying out drainage clearance works and CCTV surveys of the existing required pipes on all four road Leys, Birds Hill, Broomfield and Spicers